After all of the excitement of the delayed pour on Monday, we have had no action since. Unfortunately, we are awaiting the steel beams required for the top of the middle floors, the beam and block for the 2 balconies and the posi-joists for the floors! All of them have been on order for some while but we are in the queue for fulfilment and delivery.
Hopefully, we will start to see the missing supplies arrive next week …….